Steering committee: prepare, run and actually decide
Published on · Pilotis
The steering committee is where management makes trade-offs. Too often it becomes a progress presentation where nothing gets decided. Well prepared, it lasts an hour and unblocks the project for the weeks ahead.
What a steering committee is for
The committee is not there to tell the story of the project: it is there to decide what the team cannot decide alone. Arbitrate a budget, accept a delay, choose between two options, release a resource. If there is no decision to take, the meeting can become a simple dashboard email.
Who attends
- The sponsor, who chairs and decides
- The departments involved (business, finance, technical)
- The project manager, who prepares and presents
- Occasionally, an expert or a key supplier
Six to eight people at most. Beyond that, the committee informs but no longer decides.
An agenda that works
- 5 min · Decisions and actions from the last committee
- 10 min · Dashboard: schedule, cost, quality, risks
- 30 min · Decision points, prepared with options and a recommendation
- 10 min · Major risks and treatment plan
- 5 min · Summary of decisions and next steps
Send the pack 48 hours before: attendees arrive having read it, and the meeting is spent on decisions.
A dashboard readable in two minutes
One page, four to six indicators, a status per area (green, amber, red) and a short explanation for each amber or red. The committee must see at a glance where the project needs it. Details stay in the appendix.
After the committee
Minutes go out within 24 hours: decisions taken, actions with owner and due date, items carried over. That is the record that commits people, and the basis for the next agenda.