1. Home
  2. Blog
  3. Construction site monitoring: schedule, progress and meetings that move things forward

Construction site monitoring: schedule, progress and meetings that move things forward

Published on · Pilotis

A site rarely goes off track all at once: it slips a week on one package, then another on the next. Good monitoring makes these slips visible early, while there is still time to act. Here is a simple method, from a small renovation to a multi-package project.

Site monitoringWorks progress · structural package Progress72 % planned - - · actual Punch list closed 18 / 24 · Site meeting Thursday 9 am

1. A schedule by package, with the critical path

Break the site into packages and tasks of one to two weeks at most. Link the tasks that depend on each other (the drywaller waits for the electrician, painting waits for the drywaller): the longest chain is the critical path. That is what to watch first, because any delay on it pushes back handover.

  • Short tasks, easy to declare “done” or “not done”
  • Clear milestones: weathertight, partitions, handover
  • Visible float on tasks off the critical path

2. Measure actual progress, not gut feeling

Progress is measured in work done, not time spent. For each task, record a physical percentage (metres installed, rooms finished, points inspected). Weighting by each task gives overall site progress.

Then plot the S-curve: cumulative planned progress and cumulative actual progress, week after week. The gap between the two curves shows at once whether the site is falling behind, and by how much.

3. Short site meetings that decide

A useful site meeting fits in an hour and always follows the same order:

  • Safety: incidents, near misses, co-activity points
  • Progress by package, against the schedule
  • Blocking points and decisions to take
  • Actions: who, what, by when
  • Open and closed punch list items

Minutes go out the same day. Unfinished actions come back at the top of the next meeting: that is what moves the site forward.

4. Close the punch list before handover

Do not wait until the end to list snags. Record them during walk-rounds, with the responsible package, a photo and a closing date. A shared list reviewed every week avoids a wall of snags at handover and endless chasing.

5. The indicators to track every week

  • Actual versus planned progress (S-curve)
  • Milestones held or slipped
  • Number of open and overdue actions
  • Open snags by package
  • Safety events of the week

Five indicators are enough. Any more and nobody looks at them.

The tool to take action

S-curve

The curve of planned and actual cumulative progress, to see at once whether the project is ahead or behind.

See the tool

Or try it free: Work out your project’s earned value