OEE, overall equipment effectiveness, measures the share of time a machine really produces good parts at the right rate. It is the reference indicator to steer a line or a robotic cell.
The formula
OEE = availability × performance × quality.
- Availability = run time ÷ planned production time (stoppages: breakdowns, set-ups, changeovers)
- Performance = (parts produced × ideal cycle time) ÷ run time (slowdowns and micro-stops)
- Quality = good parts ÷ parts produced (scrap and rework)
A worked example
A line is planned for 8 hours, i.e. 480 minutes. It stops for 60 minutes (breakdown and changeover): availability is 420 ÷ 480 = 87.5%. The ideal cycle time is one minute and the line produces 380 parts: performance is 380 ÷ 420 = 90.5%. Of these 380 parts, 361 are good: quality is 95%.
OEE = 87.5% × 90.5% × 95% ≈ 75%. In other words, 361 good parts out of a possible 480.
What a good OEE means
There is no universal value: 85% is often quoted as world class for high-volume production, but many workshops start around 50 to 65%. What matters is the trend and the breakdown: knowing whether you lose mainly on stoppages, speed or quality.
Common pitfalls
- Excluding changeovers from planned time: OEE looks better, but the loss disappears from view
- Using a “realistic” rate instead of the ideal cycle time
- Averaging OEE across different machines
- Measuring without analysing: OEE is there to choose the next improvement project
Take action
Once losses are ranked, pick the biggest: SMED for changeovers, basic maintenance for breakdowns, problem solving for scrap. The free OEE calculator gives you the figure in seconds.
The tool to take action
Work out your takt time and OEE
Work out your takt time and OEE for free: availability, performance and quality of your line or machine, with how to read them.